Zenit Madencilik plans to increase the capacity in the enrichment facility of Kızıltepe Gold and Silver Mine operating near Yolcupınar and Çoturtepe neighborhoods located in Balıkesir, Sındırgı.
It has been learned that the current capacity of the facility will be increased from 210,000 t/y to 510,000 t/y production. In this case, adding a 300,000 t/y capacity mill to the existing 210,000 t/y capacity mill, total mill capacity will be increased to 510,000 tons / year with two operating mills.
The ore processing capacity of the ore enrichment facility, which is planned to increase the capacity, was determined as 1.457 tons / day, considering that the facility will work 350 days a year.
Among other information obtained, the project cost, which will create an additional employment of 74 people, is 44 million TL in total for Zenit and the subcontractor.