Alacer Gold shared a report about the activities it carried out in the second quarter of 2020 in  the Çöpler Gold Mine. The information highlighted in the report was as follows:

Gold production from the Çöpler project in the second quarter of the year meet the company’s 2020 guidance and were realized as 79,349 ounces. The company noted that 57,681 ounces of this production was carried out from the sulfide plant and 21,668 ounces from the oxide plant. Total gold production between 1 January and 30 June realized as 167,212 ounces. 46,731  ounces of this production realized from oxide facility and 120,481  ounces from sulfide facility.

The company emphasized that emphasized that 3.9 million people / hour and 309 days were left behind in the enterprise without a lost time injury accident.

Sharing the affects of Covid-19 on mining operation the company stated that  operations continued uninterrupted through the period. However, COVID-19 restrictions and diversion of the remaining resources to manage COVID-19, and delayed improvement initiatives had some impact on operational performance. Proactively sending home older staff, and those with existing health conditions, also had an impact on mining operations through a shortfall of mine operators. This contributed to a decision to adopt a revised mine plan to diversify ore sources.

Stating that the “Autoclave 2” was shut downed for the first time in March and that internal audit was carried out, Alacer Gold stated that the equipment is in very good condition. Due to good condition of “Autoclave 2”  planned shut down for “Autoclave 1” was postponed.

The company reminded the merger agreement signed on May 11, 2020 between Alacer and SSR Mining.  The combined entity will continue as SSR Mining Inc. and will be headquartered in Denver, Colorado with a corporate office in Vancouver, British Columbia and will be led by Michael Anglin as Chairman and Rod Antal as President and CEO

The company stated that it continued its focus on improving and extending oxide gold production in future years beyond the current Çöpler oxide reserves by accelerating the development of a number of near-mine targets within the Çöpler pits and surrounding areas with 15 drill rigs currently active.

Alacer Gold continues the drilling at the Ardıç deposit in Q2. Ardıç has an interim Indicated Mineral Resource of approximately 817,000 ounces of gold (15.86 million tonnes at 1.60 g/t of gold (“Au”) and an Inferred Mineral Resource of approximately 594,000 ounces of gold (8.80 million tonnes at 2.10 g/t Au).

Stating that they are planning to publish an updated technical report in the second half of 2020, Alacer stated that the report will include preliminary development plans for Ardıç, updating the performance expectations of the Çöpler Sulfide Plant, incorporating a proposed supplemental flotation circuit, as well as opportunities for tailings storage expansion and for resource conversion in Çöpler projects.

The company also informed that the constraints for the project of 25 million tonnes of Çöpler heap leach pad expansion, which will be built gradually in the coming years and will provide an additional 5-year additional oxide processing capacity, have eliminated and first stage of construction is completed. Detailed engineering and permit process is ongoing parallel to construction.

The company also noted that they continued to investigate actively the many prospective exploration targets across Turkey.

 

Previous articleLiberty Gold Announced Receiving the Second Payment and Closing of the Sale Agreement on Halilağa Project
Next articleOriole Resources and Anadolu Export Signed a Sale Agreement on Karaağaç Project