Ariana Resources, the exploration and development company with gold mining operations in Turkey, shared its 2019 production guidance for the Kiziltepe Mine.
According to information company shared, 2019 gold production guidance for Kiziltepe is approx 25,000 oz Au. This is approx 21% above feasibility plan for the third year of operations.
The company forecasts includes approximately 13,000 tonnes of average monthly production of ore and Production is planned to peak during fourth quarter of 2019.
Ore throughput of the mill during 2019 is expected at approx 195,000 tonnes. This represents a 30% increase over the feasibility plan.
Average grade of gold expected to be mined during the year is expected at approx 5 g/t Au and gold recovery is expected to exceed 90%.
Ariana Resources will continue open pit mining with focusing on the Arzu South pit during 2019, with preparations being made to commence mining on satellite pits from early 2020.
Ariana Resources Managing Director, Dr. Kerim Sener commented about 2019 mmented:”Following the quarterly operational update, as announcedn 22 February 2019, in which we confirmed the full year 2018 Kiziltepe production figures, we are very pleased to report our production guidance for 2019. Advancing on the Company’s positive finish to 2018, the Kiziltepe mine continued to perform exceptionally well, despite a very wet winter period during Q4 2018 and into Q1 2019, and we look forward to building on this strong operational track-record. Notably, our gold production guidance for the JV is up 25% from last year’s guidance, and is estimated at circa 25,000 oz for the year, reflecting a further increase in expected grades as we mine deeper into the Arzu South pit and the maintenance of high monthly mill throughputs. Although ore output from Arzu South will be variable through the year due to the pushbacks required to accommodate the final stage of mining, current stockpiles are expected to provide for any shortfalls in output such that mill throughput can be maintained at the highest levels through the year.
As a low-cost open pit operator, ranked in the lowest quartile of cash costs globally, the JV continues to target increases in production and life of mine. We are pleased to note that our plans for advancing production from some of our satellite pits are at an advanced stage and we look forward to commencing work in these areas towards the end of this year. Meanwhile repayments of the JV loan to Turkiye Finans Katilim Bankasi A.S. are over half completed, with the balance largely being paid down by the end 2019.”