Ariana Resources, the exploration and development company with gold mining operations in Turkey, announced its preliminary production results for the fourth quarter of 2018 for the Kızıltepe Gold Mine which is part of the Red Rabbit Joint Venture with Proccea Construction Co. and is 50% owned by Ariana through its shareholding in Zenit Madencilik.
Ariana Resources produced a total of 27,110 ounces of gold in 2018. Preliminary results shows that it exceeded their initial full year production guidance of 20,000 ounces of gold by 7,110 ounces; representing an increase of approx. 36%.
While Gold production on Kızıltepe was 7,556 ounces in third quarter, it was realized as 7,517 ounces in last quarter of the year.
Total ore processed for the quarter was 49,717 tonnes at an average head grade to the plant of 5.23 g/t gold.
Open pit ore mined for the period ended 31 December was approx 63,760 tonnes, at an average mined grade of 4.53 g/t gold, and total material movement for the quarter was 719,370 tonnes.
Average gold recovery rate in the facility for the quarter remains high at 91.6%.
Ariana Resources Managing Director, Dr. Kerim Sener commented about the preliminary results: “The last quarter of 2018 marks an important milestone for the Company, having exceeded our forecast production for the year by a very substantial margin. It also coincides with the repayment of half of our development capital loan of US$33 million, with the balance to be repaid largely during 2019. The past year has seen the Joint Venture achieve several successes, quarter on quarter, including an annualised increase in mill throughput to 200,000 tonnes per annum. We look forward to the continuation of these very positive developments. We take this opportunity to thank both our dedicated JV team and our partners, Proccea Construction Co., for their diligence and focus during the year.
“We begin 2019 on firm-footing and we are very excited about the year ahead. We are expecting to publish 2019 production guidance in due course.”