Ariana Resources, the exploration and development company with gold mining operations in Turkey, shared its preliminary production results for the quarter ended 31 March 2018 for the Kiziltepe Mine which is part of the Red Rabbit Joint Venture with Proccea Construction Co.

Gold production in Kızıltepe increased %8 compared to previous quarter and reached to  4,866 ounces. The Company stated that its full year production guidance of 20,000 ounces Au stands same in the light of this this production figures.

The company stated  that total processed ore for the quarter was 44,897t  with an average head grade of 3.85 g/t Au and processing performance meets their  expectations.

In the quarter,  open pit ore mined was c. 68,600t, at an average mined grade of 4.5 g/t Au. Comparing the previous quarter, this production figure shows a 37% increase in tonnes and a 32% increase in grade.

The company stated average metallurgical plant recovery of gold for the quarter  ended 31 March 2018 was 95.1%.

Commenting latest production results  Ariana Resources Managing Director Dr. Kerim Sener, said: “The performance of Kiziltepe continues to exceed feasibility expectations and this quarter of production marks a solid start to 2018.  First quarter gold production was 8% higher than the previous quarter, augmented by a 4% increase in gold recovery from the processing plant.  During the current quarter, we are expecting output to increase further based on our 2018 mining schedule and particularly as we start to access higher grade areas of the Arzu South vein.  Consequently, we are confident in delivering positively against our production guidance for 2018.”