Ariana Resources, the exploration and development company operating in Turkey,  announced its operating results for the quarter ended 31 March 2018 for the Kiziltepe Mine.

The company had previously announced production and sale of 4,866 oz gold during the quarter ending 31 March 2018 with an 8% increase comparing to previous quarter.

Ariana stated that operational mill availability running at 98% and utilization at 96% during March. Also 44,897 tonnes ore milled in first quarter which is  20% higher than the feasibility forecast, on an annualized basis. Milled ore grades were 3.85 g/t Au in the quarter.

Approximately 62,200 tonnes of ore at a weighted average grade of 3.09 g/t Au stockpiled for future use. This amount represents about four months of production, the company said.

Gold recoveries from process was higher than expected at the end of the quarter with approximately 95%.

Production of ore from the open-pit achieved an average rate of 20,300 tonnes per month in first 4 month of the year. The month with highest rate was  February with over 28,800 tonnes.

The company stated that second-stage Tailings Storage Facility (“TSF”) dam wall completed during Q1. Construction of  Stage 2a TSF liners installation will start in Q2.

Dr. Kerim Sener, Ariana Resources Managing Director, said: “This past quarter has been another successful period of operation for the Kiziltepe Mine.  Due to the strong operational cash flow from Kiziltepe, we have been receiving intercompany loan repayments from the JV to our wholly owned subsidiary, Galata Madencilik San. ve Tic. Ltd. during Q1 2018. These repayments are continuing and are expected to be made on a monthly basis, enabling the Company to become self-financing during 2018.”

For Further Information: Ariana Resources