Acacia Mining, operating in the Hanönü district of Kastamonu province, announced that it successfully accomplished its first copper concentrate production in the Gökırmak Copper Project on March 4.
The company had been continuing transportation of the ore to the flotation facility since realizing first contact with the ore in the first quarter of 2018.
Commissioning of the ball mill with 4400 KW motor power, considered one of the most important steps of production according to the information given by the company, was completed on 22 February and the trial and commissioning works at the plant have continued until the beginning of March.
The operation was established in 2007 to operate the copper deposit discovered in the district of Hanönü and It continues its activities with participation of İlbak Holding In 2011 and Akfen Holding in 2017.