A major industrial project is being implemented in the Zhambyl region of Kazakhstan, involving the construction of a soda ash production plant, one of the largest chemical initiatives in Central Asia.
Kazakh company BI-Industrial is participating in the project under an EPC framework, responsible for delivering key infrastructure required for commissioning the production facilities. The project investor is Qazaq Soda LLP, part of Türkiye-based COREX Group, while China’s CAMCE serves as the general contractor.
The first phase of the plant, scheduled for launch in September, will have a production capacity of 500,000 tonnes per year. In subsequent stages, total output is expected to reach up to 3 million tonnes annually, enabling Kazakhstan to fully meet domestic demand and develop export capacity.
According to Qazaq Soda Operations Director Yusuf Ceylan, the Zhambyl region was selected following a detailed assessment due to its logistical advantages, favorable climate conditions, and access to key raw materials. The proximity of salt deposits, water resources, and limestone contributes to an efficient production chain.
Investment in the first phase is estimated at approximately USD 400 million, while total investments across all stages are expected to exceed USD 2 billion. Financing has been secured through an international banking consortium including Bank of China, ATB Bank, the Development Bank of Kazakhstan, and Halyk Bank.
Kazakhstan currently imports around 400,000 tonnes of soda ash annually. The product is widely used in the glass, metallurgical, and chemical industries, as well as in water treatment. Upon completion, the project is expected to shift the country from a net importer to an exporter of soda ash.
The EPC model entails full contractor responsibility for engineering, procurement, construction, and commissioning, requiring integrated engineering solutions and strict project management. BI-Industrial is responsible for five key facilities: a residential camp covering 8.7 hectares, a 25-hectare solid waste storage site, an 800-hectare evaporation pond, a limestone crushing and sorting complex, and railway infrastructure.
The project incorporates environmental protection measures, including isolated waste storage systems using geomembranes and geotextiles, water treatment systems, and emissions control technologies. The production site is located at a distance from populated areas.
During construction, more than 300 personnel and 65 units of equipment are engaged, with most workers recruited locally. Once operational, the plant is expected to employ over 380 people, with the majority being Kazakh specialists.
BI-Industrial, part of BI Group, has previously delivered several industrial projects, including tire production facilities and processing plants. Its involvement in the soda ash project demonstrates the capacity of Kazakh EPC contractors to execute large scale industrial developments in cooperation with international partners.