ETİ Bakır’s Mazıdağı Metal Recovery and Integrated Fertilizer Facilities project is located in the Mazıdağı district which belongs to Mardin province of Turkey. The plant has process capacity of 550 thousand tons phosphate rock per year and has production capacity of 750 thousand tons of fertilizer per year.
Starting in the first quarter of 2015, The project completed in the first quarter of 2019. Mazıdağı Metal Recovery and Integrated Fertilizer Facilities comprise of 5 main factories and 14 units of the auxiliary facilities. Main facilities are consist of sulfuric acid plant, phosphoric acid plant, ammonia plant, fertilizer plant, and hydro-metallurgical plant. The auxiliary facilities are consist of demineralized water production plant, chemical water treatment plant, water cooling plant, condensate purification plant, steam turbine and gas engine, auxiliary boiler, natural gas distribution stations, air compressor plant, pyrite and ash transport units, fire reservoir and distribution system, main water tank and water wells, phosphate beatification plant, 154 Kv switchyard, and packaging facility. The construction of the facility completed with commissioning in 50 months and achieved 20 million man-hours. Total investment cost of 1.1 billion USD makes the project highest budgeted project in Eastern Turkey.
5 different leading engineering firms worked in the design of the facilities. The complex has 625 thousand m2 of the construction area and 300 thousand m3 of concrete have poured while 30 thousand tons of rebar have used. 200 thousand m2 roof and facade cladding units have installed. Besides, 650 thousand m2 of chemical coating works have been one of the essential elements of the project.
22 thousand tons of equipment and 20 thousand tons of structural steel have been erected. 500 thousand dia inch of pipes and 18 thousand valves have been installed. 2,500 km of cables have been spanned. 2 million m3 scaffolding have been installed for erection works. One of the most challenging parts of the project was the commissioning process, which had 2,000 test packages.
Furthermore, 14 thousand activities have been created at the scheduling program ASTA by Powerproject and updated weekly bases thru the online web-based process. The project have been monitored from the first scratch to completion. Weekly progress reports in the operation includes not only updated weekly activities but also risk reports shows the items may affect the critical path or nearly critical path activities. This upgraded weekly reports allowed the management team to intervene early to the activities may cause delay or additional cost.
Over 2,000 contracts and addendums have been prepared, and equipment/services have been purchased from the United States to England, from Germany to Japan, from India to South Africa.