Ariana Resources, the exploration and development company with gold mining operations in Turkey, shared its unaudited interim results for the six months ended 30 June 2019.
The company’s gold production in H1 of 2019 is increased 14% compared the same period of 2018, to 13,734 oz Au.
Gold production guidance for 2019 for the Kızıltepe Mine is announced as c. 25,000 oz Au. The company expects to meet the guidance by the end of Q4 2019.
In first half of the 2019, Ariana obtained two new 10-year operating licences for the Salınbaş Gold Project. The company stated that they are working on Environmental Impact Assessment and Pre-Feasibility Study. The company also emphasized that Environmental Impact Assessment of Tavşan is nearing completion.
Michael de Villiers, Chairman, commented about Ariana Resources first half results: “It is once again my pleasure to report on another six months of exceptional results from both our operating mine and our exploration and development activities. The Kiziltepe Mine has increased output by 14%, compared to the same period last year, and I am pleased to confirm that we remain on track to produce c.25,000oz (gross to the JV) of gold for the year. This has been achieved whilst realising an average operating cost for the period under US$500 per ounce, making us one of the lowest cost gold producers globally.
We are making significant progress on paying down the US$33 million construction capital loan for the mine, with US$25.8 million, or 78% of the loan, now paid post-period end. We remain fully on track to repay the remaining construction capital loan by April 2020, placing us in an even stronger position for FY2020. This financial strength is expected to support our various exploration and development programmes across our Turkish portfolio and underpin the diversification of the Company’s portfolio outside of Turkey.
We remain excited by the highly prospective Salinbas Gold Project, which we believe has the potential to become a significant new gold mine producing at a rate of 50,000 oz per annum over a 10-year life of mine. The commencement of an Environmental Impact Assessment and a Pre-Feasibility Study during Q4 2019, will confirm the potential of the Salinbas Project and determine the next steps for bringing this exciting project into development.
Commodity market conditions have been very favourable in the first half of the year, with the gold price having risen up to 22% to a high of US$1,552 per ounce during the period. We expect that commodity price strength will continue for the medium-term and this will continue to maintain our positive momentum into the second half of the year.
I would like to take this opportunity to thank Ariana’s production and exploration teams for their hard work and dedication over the period and also to the Company’s board for their continued support and hard work.”