Centerra Gold, a Canadian-based gold mining company which is building its 100% owned Öksüt Gold Mine in Turkey, shared an update on its 2018 production results and 2019 guidance.

at Öksüt, the company’s planned capital spending for 2019 is expected to be approx $123 million . The total cost of construction is expected to be approximately $220 million (Including contingency) to first gold pour which is anticipated in the first quarter of 2020.

by the date of December 31, 2018  38% of the construction activities at the Öksüt site  complete. According to the report recent situation of the construction works; the main access roads substantially completed; haul road construction is
ongoing, heap leach phase 1 area stripping is completed, crusher equipment is onsite and placed on the concrete foundations; ADR plant steel is erected; construction of the administration and truck shop campus, and electrical substation is ongoing; and various earthworks activities for the heap leach pad, ore stockpiles and waste dumps continue. In 2019, stripping is expected to commence in June and ore stockpiling in July.

The company also shared its exploration expenditures. According to the information shared by the company, planned exploration expenditures at Öksüt for 2019 are expected to be $2.5 million.